Mo-Dot Planned Road Work for Northwest Missouri, March 29 – April 4

Andrew County

Interstate 229 – Resurfacing project from I-29, north of St. Joseph, to Route 371 (mile marker 14 to 3) through mid-September.

I-29 – Bridge replacement project northbound over Hopkins Creek, mile marker 58, through September 2021. Traffic is head-to-head in the southbound lanes. This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.

Route T – Drainage work from County Road 408 to County Road 409, March 29

U.S. Route 169 – Driveway tube replacement across from County Road 291, March 31

 

 

Buchanan County

U.S. Route 36 – Guardrail and pavement repair between the Missouri River and 0.75 miles east of Route AC through early August. A 12-foot width restriction is in place.

I-229 – Resurfacing project from Route 371 to I-29, north of St. Joseph (mile marker 3 to 14) through mid-September.

I-29 and U.S. Route 36 – Pothole patching, March 29 – April 2

Route 31 – CLOSED for a culvert replacement from Route NN to Route T, March 31, 7 a.m. to 3:30 p.m.

 

 

Caldwell County

U.S. Route 36 – Pavement repair through Caldwell, Livingston and Linn counties through mid-June. There will be intermittent lane closures with a 14-foot width restriction.

 

 

Carroll County

Route Z – CLOSED until further notice from Route C to County Road 217 due to damage caused by a roadway slide and ongoing geological studies.

 

 

Chariton County

Route 139 – CLOSED for a bridge replacement project at the Grand River Overflow Bridge through July. This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state. More info: https://www.modot.org/chariton-county-route-139-grand-river-overflow-bridge

Route 5 – Bridge flushing over Doxie Creek, Little Chariton River, Little Chariton River Overflow, Puzzle Creek, and Shannondale Branch, March 29

Route 129 – Drainage work from U.S. Route 24 to Lusher Street, March 29

U.S. Route 24 – Bridge flushing over the Chariton River, Long Creek, and Middle Fork Chariton River, March 30

U.S. Route 24 – Bridge flushing over Mussel Fork River, March 31

U.S. Route 24 – Drainage work from Keytes Street to Cleve Iman Lane, March 31

U.S. Route 24 – Drainage work from Route FF to Jordan Road, April 1

Route 5 – Bridge flushing over Cottonwood Creek and Mussel Fork Creek, April 1

 

 

Clinton County

I-35 – Pavement repair from Route 116 to Shoal Creek through mid-July. There will be intermittent lane closures with a 12-foot width restriction.

 

 

DeKalb County

Route A – CLOSED for a bridge deck replacement project at the Lost Creek Bridge, north of Maysville, through June 2021. This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state. More info: https://www.modot.org/dekalb-county-route-bridge-over-lost-creek 

 

 

Gentry County

Route 85 – Pothole patching from U.S. Route 136 to Route A, March 29 – 31

Route A – Pothole patching from Route 85 to Route Z, March 31 – April 2

 

 

Grundy County

Route Y – CLOSED for a culvert replacement from Northeast 30th Street to Northeast 20th Street, March 29 – 30, 7 a.m. to 3:30 p.m. daily

Route 149 – Bridge maintenance over Cattail Creek, March 29 – April 2

Route Y – CLOSED for a culvert replacement from Northeast 37th Street to Northeast 30th Street, March 31, 7 a.m. to 3:30 p.m.

Route Y – CLOSED for a culvert replacement from Northeast 50th Street to Northeast 37th Street, April 1, 7 a.m. to 3:30 p.m.

Route Y – CLOSED for a culvert replacement from Northeast 76th Street to Route O, April 2, 7 a.m. to 3:30 p.m.

 

 

Harrison County

Route EE – CLOSED for a bridge deck replacement project over Panther Creek, near New Hampton, through late April. This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state. More info: https://www.modot.org/route-169-and-route-ee-bridge-deck-replacement

Route N – Bridge deck repair over I-35, March 29 – April 2

Route 146 – CLOSED for a culvert replacement from U.S. Route 136 to Gilman City, April 1, 7 a.m. to 3 p.m.

 

 

Holt County

U.S. Route 59 – Shoulder work from U.S. Route 159 to Mound City, March 29 – April 2

 

 

Linn County

U.S. Route 36 – Pavement repair through Caldwell, Livingston and Linn counties through mid-June. There will be intermittent lane closures with a 14-foot width restriction.

Route V – CLOSED for a culvert replacement from Jasper Drive to Ingel Road, March 29, 7 a.m. to 3:30 p.m.

U.S. Route 36 – Bridge flushing from Danube Drive to Route 130, March 31

 

 

Livingston County

U.S. Route 36 – Pavement repair through Caldwell, Livingston and Linn counties through mid-June. There will be intermittent lane closures with a 14-foot width restriction.

U.S. Route 36 – Bridge flushing from Route C to U.S. Route 65, March 29 – 30

U.S. Route 36 – Bridge flushing from U.S. Route 65 to Route 139, March 31 – April 2

 

 

Mercer County

Route JJ – Bridge scour repair project at the two bridges over Honey Creek, near Spickard, through mid-April March. There is a 10-foot width restriction in place. Traffic will reopen to two lanes each evening.

 

 

Nodaway County

Routes C and UU – Pothole patching, March 29 – 31

Route JJ – Drainage work from Juniper Road to Route 148, March 31 – April 1

Route D – Pothole patching, March 31 – April 2

 

 

Putnam County

Route Y – CLOSED for a bridge deck replacement project at the North Blackbird Creek Bridge through May 2021. This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state. More info: https://www.modot.org/putnam-county-route-y-north-blackbird-creek-bridge-deck-replacement-project

Route K – CLOSED for a culvert replacement from Route KK to Route EE, March 29, 8 a.m. to 2:30 p.m.

Route K – CLOSED for a culvert replacement from Route EE to Route EE (Sullivan County), March 30 – 31, 8 a.m. to 2:30 p.m. daily

Route E – CLOSED for a culvert replacement from Route 139 to Route T, April 1 – 2, 8 a.m. to 2:30 p.m. daily

 

 

Sullivan County

Route PP – CLOSED for a bridge replacement project over East Medicine Creek through mid-April. This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state. More info: https://www.modot.org/sullivan-county-route-pp-east-medicine-creek-bridge

Route K – CLOSED for a culvert replacement from Route BB to Marble Road, March 29, 8 a.m. to 3 p.m.

Route T – CLOSED for a culvert replacement from Rolling Road from Shell Road, March 30, 8 a.m. to 3 p.m.

Route K – CLOSED for a culvert replacement from Route EE to Route EE (Putnam County), March 30 – 31, 8 a.m. to 2:30 p.m. daily

Route T – CLOSED for a culvert replacement from Tiger Road to Ember Road, March 31, 8 a.m. to 3 p.m.

Route V – CLOSED for a culvert replacement from Willow Road to Route O, April 1, 8 a.m. to 3 p.m.